logo

Röchling adds production hall at Peine site in Germany

17 March 2017

Automotive injection moulder Röchling has opened a new production hall in Peine, Germany, to cope with continuing demand growth.
The new hall has a floor space of 1,800 square metres, extending the total production area at the Peine facility to 12,100 square metres. The hall is equipped with a 50-tonne crane system and its own material supply and a drying area.
In a news release, Röchling Automotive said: “The machinery at the new production hall comprises two large-scale machines and a number of subsequent processing machines, which will be used to produce vehicle parts for two major automotive manufacturers.”
Röchling Automotive acquired the land for the new facility in 2014. It is directly connected to the company’s new logistics hall, which was built in spring 2016. Röchling said it has invested a total of €13.6m on constructing the two halls.
The production hall had its official opening ceremony on March 13, following a construction period of eight months.
“In Peine, we had reached the limits of our production capacity. With the new hall, we are now able to successfully fulfil all incoming orders,” said Erwin Doll, CEO of the Röchling Automotive Group.
The Peine facility employs a workforce of approximately 350 people and produces about 27 million parts a year.